| 2009年12月13日 レンガ到着 |
>
![]() |
![]() |
![]() |
>
| 2010年1月2日 基礎工事始まる |
>
![]() |
![]() |
![]() |
>
| 2010年2月7日 基礎工事途中 |
>
![]() |
![]() |
![]() |
>
![]() |
![]() |
![]() |
>
| 2010年2月19日 基幹工事進行中 |
>
![]() |
![]() |
![]() |
>
| 2010年3月15日 基幹工事進行中 | >
![]() 2010年 3月24日 |
![]() |
![]() |
>
| > |
![]() 2010年 4月3日 |
![]() |
![]() |
>
| > |
![]() 2010年4月7日 |
![]() |
![]() |
>
| > |
![]() |
![]() |
> |
| 2010年4月25日 | >
Thursday, May 06, 2010 Please find attached informations for
a) New bore well to ensure full water for all Katagiri project and
specially the water supply for the school.
The 'centering' for the roof slab is in good progress. The BEAM for the
roof is 60% completed.
The 'false' ceiling for the roof slab is ready schedule 19th May. All roof
slab works should be completed by May 29th as per schedule.
It would be appreciated if funds were available soon please.
Kindest regards,
Rose
|
>
![]() |
![]() |
![]() |
>
|
This young man is a junior Engineer. He is the building site supervisor. He checks that the contractor is doing correct. |
We have now completed the new water bore well. This will ensure sufficient water for all Katagiri project buildings and the bathroom and toilet in the new school the Bore well is 70 mt deep. |
The Director, Mr. Rose discuses the plan for drilling. |
>
![]() |
![]() |
![]() |
>
|
The work is getting ready for the roof. We say roof slab. All material are on site. We will know the date for making the slab on Friday. |
These are the very strong special pipes that went into the ground. At the top there are steel galvanized pipes for 7 mt. All this was supervised by the Director. |
The children celebrated when the water was found and the pipes put in and all completed. (Photographs by Vasu and computer Photoshop by Subbu and 6th class children.) |
>
![]() |
![]() |
![]() |
>
| 2010年6月11日 | >
|
Wednesday, June 16, 2010 School Roof Construction Greetings, We have completed the first section of the school roof. It took 8 hours of
work and 22 men.
It was a very interesting day. NO rain, just cool. Wonderful.
Regards
Rose
|
>
![]() |
![]() |
![]() |
>
| Cement blocks with metal chips | All iron rods are cleaned before using | View from roof of school showing Cement Truck delievering concrete.Ruth on left and Rose (Director) on right.. | >
![]() |
![]() |
![]() |
>
| Checking the levels of steel mesh before concrete | Pipe on left, ready to bring concrete |
From Cement truck, concrete pump to delivery tank (right) | >
![]() |
![]() |
![]()
|
>
| The Head Mason on right, Cement Truck Driver, Mr. Veer Raju Contractor, Labor in Charge fo Masons | >
| > |
| Thursday, February 03, 2011 7:30 PM Dear Mrs. Katagiri san, School building is being plastered, final cement coatings for walls. Regards Vasu Gabriel |
![]() |
![]() |
>
| > | ||
2011年4月の現状![]() |
![]() |
![]() |